Project Scope: Directional drill/ Trench
This work included the following: bored 1-4″ from a vault 520 feet to a new 660. Bored 1-4″ from the 660 100 feet to a to a pole. Bored 1-4″ from the 660 230 feet. Trenched 1-2″ 1548 feet off of 1 pole, 4 existing vaults and 1 new 504. Bored 1-4″ 175 feet. Bored 1-4″ from pole 142 feet to a vault. Bored 1-2″ from a vault 98 feet then turn and bored an additional 118 feet to a vault.
Scope: Install Express Underground Feeder Constructed new express underground 34.5kv feeder. Behind the substation, installed a single phase underground termination and 1/0 cable to intercept...